7-21-02
 | |
The pier base was 34” x 40” or so, excavation was a little exciting with the pick-axe.
|
|
9-1-02
 | |
The rebar was set and ready for the pour.
|
|
9-1-02
 | |
The pour! Nine cubic feet or so.
|
|
9-1-02
 | |
The finished base of the pier.
|
|
9-2-02
 | |
The form set for the column of the 48" pier.
|
|
9-2-02
 | |
The center tube is placed in the mold, later to anchor the German equatorial mounting.
|
|
9-2-02
 | |
A close up view.
|
|
9-2-02
 | |
All done!
|
|
9-8-02
 | |
The pier revealed, looking east.
|
|